Autumn/Winter 2026

The latter part of this year and into early next will see work commence on the apartments on the eastern side of the site. We anticipate that reinforced concrete frame works will commence mid November, with brickwork on Block B also starting at this time. December should see scaffold go up on Block B with the first floor planks for this building likely to go in late January 2027.

As work is now starting in this location, we are able to apply for a temporary builders supply of electricity here. This means that instead of having to rely on solar lighting for the station footpath (which unfortunately has been vandalised on several occassions previously), we can install some safety lighting along our side of the boundary to illuminate the footpath. 

We also expect a planning decision on our application for "Phase 2" at Elizabeth Square prior to Christmas.